UNITED STATES v. CALLAHAN WALKER CONSTRUCTION CO. CERTIORARI TO THE COURT OF CLAIMS. No. 65. Argued October 23, 1942. Decided November 9, 1942. Under the Government construction contract here involved, an “equitable adjustment” for the extra work performed by the contractor required merely the ascertainment of the cost of digging, moving, and placing earth, and […]
Articles Tagged: 317 U.S. 56
317 U.S. 56
317 U.S. 56 317 U.S. 56 63 S.Ct. 113 87 L.Ed. 49 UNITED STATESv.CALLAHAN WALKER CONST. CO. No. 65. Argued Oct. 23, 1942. Decided Nov. 9, 1942. Rehearing Denied Nov. 23, 1942 See 317 U.S. 710, 63 mS.Ct. 203, 87 L.Ed. —-. Messrs. Francis Biddle, Atty. Gen., and Richard S. Salant, of Washington, D.C., for […]